Qlogic Storage Networking (Unified Fabric Pilot) Guía de instalación Pagina 49

  • Descarga
  • Añadir a mis manuales
  • Imprimir
  • Pagina
    / 76
  • Tabla de contenidos
  • MARCADORES
  • Valorado. / 5. Basado en revisión del cliente
Vista de pagina 48
5–Validation Methods for DCB and FCoE
Validation Step 5—ETS Verification
51031-00 A 5-19
2. Run all the tests with the Write configuration (Figure 5-18), and then repeat
all the tests with the Read configuration (Figure 5-19).
Figure 5-18. Verifying ETS with Write Operations to the Storage
Figure 5-19. Verifying ETS with Read Operations from the Storage
3. Start the FCoE and other traffic (TCP, iSCSI) simultaneously in the MLTT
application to saturate the link.
4. Use TraceControl to monitor link throughput.
5. Pause I/O from each application in a round-robin manner, and verify that the
free bandwidth is being distributed to the other traffic classes. Figures 5-21,
5-22, and 5-25 show the results of pausing I/O in a round-robin manner.
6. Capture a trace.
4Gbps
10Gbps
4Gbps
10Gbps